General Contractor
Nishimatsu Lum-Chang J.V.
Client
National Library Board
Engineer
Maunsell Consultants
Architect
DP Architects
Designer
Meinhardt Consultants
Total Tonnage
6,500 tons
Subcon Start Date
2001 December
Subcon Completion Date
2004 September
|
For the National Library Board project, Yongnam fabricated and erected one of the
largest built-up plate girders in Singapore. A 134 tons steel plate girder, 35m long and
3m high was fabricated from 120 mm thick steel plates. This project consists of about
6,500 Tons of steel forming the main structure of the two 16 storey tower blocks.

|